Worklist:
Review extension framework for Edwards boards.
Infill voids with foam.
Check ballast from last week.
Design, make and install scenic point equipment for new points.
Geoff had been busy making the extension frame for Edwards as previously described.
While Geoff worked on the previously laid ballast to remove stray 'stones', Stephen started infilling the Edwards framework voids with insulation foam blocks.
The new quarry water panel and how it will fit into the enlarged hole was discussed. A sheet of Perspex was found which would be perfect for the base.
Geoff moved on to the scenic point operation equipment and assessed the options and available fittings. Finally, a manual throw lever was agreed and found for the point in the sidings. However, it was a chunky white metal unit rather than a smaller/neater plastic unit, so Geoff filed away the visually surplus material. Components left over from the station lever frame were found and assembled into a 3 lever frame for the mainline point into the sidings. (1 lever for the frame lock, 1 for the tie-bar and one for the point lock). The latter caused Geoff the biggest problem, as it operates at 90 deg to the tie-bar and required cranks to achieve it. A choice of cranks were discussed and made. The tie-bar lock itself was made from plasticard and fitted in place.