Wednesday 17th December 2025
Wednesday 10th December 2025
Unfortunately, this week, there is nothing 'interesting' to display as we continued to investigate the existing track sections and wiring within the crossover, in order to bring it in-line with the other points on the layout. This was made a bit more difficult as the crossover spans two boards and links have to be used.
A new track break was cut and some repairs were undertaken, but it was a frustrating session and the crossover is still not functioning fully.
Wednesday 3rd December 2025
![]() |
| How the cross-over rails are electrified and the 'simple' switch wiring. |
Wednesday 19th November 2025
Progress 'normalising' the diamond crossover.
The first job was to cut away the insulating material in the two frogs, which a disc cutter in the right hands made short work of. Various pieces of NS rail laid upside-down were trialled to fill the gap and create the new frog. These will be filed down to the correct shape in due course.
![]() |
| Insulation removed (left) and frog rebuilt (right). |
The rewiring of the crossover is to suit the future switching arrangement designed by Geoff. A three position rotary switch on the control panel will enable:
Position 1. Diagonal right to left track route.
Position 2. Middle, straight through running on both front and rear tracks.
Position 3. Diagonal left to right track route.
Wednesday 12th November 2025
Today, we started to modify Johns points, which started with a discussion about the problems and the solutions.
![]() |
| John's configuration |
![]() |
'Normal' configuration on all other boards |
![]() |
| Cutting the blades unit to allow for its removal and to form the electrical separation required. |
![]() |
| Unsoldering the solid tie bar for reusing the blades. |
![]() |
| The cleaned-up point ready for reassembly. |
![]() |
| The blades were soldered to pivot pins in the new sleeper tie bar. These reduce the stress on the printed circuit board as the blades move. |
Wednesday 5th November 2025
Wednesday 29th October 2025
![]() |
| The substantial XLR plugs and sockets |
![]() |
| The old DIN plug on one of the 5 controllers. |
Wednesday 22nd October 2025
Finish installing the replacement uncoupling magnet in the platform.
This was a permanent magnet that has become a nuisance as it regularly uncouples trains running over it rather than when the train stops and backs-up.
The new magnet frame had been printed and assembled.
The unit was then screwed into place and tested for the correct amount of movement.
Following the recent exhibition, there were a lot of questions asked by the public, which is always nice. However, sometimes we didn’t have enough time to answer properly or in enough detail, so we are investigating the provision of ‘Viewing Notes’ on the blog so that they can be accessed on a phone. Sample items have been added for testing. We envisage a viewer accessing the blog using the existing graphical link on the layout front and then accessing the item relevant to where they are along the layout.
Some are informative and some are to encourage the viewer to look at or into something to appreciate more of the layout. The topics are on the right hand panel of the blog.
Wednesday 15th October 2025
The post exhibition meeting means unpacking and stowing away. The back-to-back board units were separated, checked for damage and put away. Everything else was consigned to its usual place.
The wooden frame unit (AA-BB) was assembled to form the base for the workshop centre table. As there was a minor delay when assembling the unit at Farnham, the legs were given additional markings to ensure it goes together smoothly next time.
Geoff offered an idea for the next project. The fixed uncoupling magnet at the end of the main platform (Fiddleyard end) had been causing trains to be split when not required, which annoyed him greatly. The station board was up-ended, the area assessed and the fixed magnet removed.
![]() |
| Standard fixed magnet unit... |
![]() |
| ...And the hole it came out of, tight to the timber frame. |
Geoff confirmed that there was space for a hinged unit and set about finding a spare. However, it was then noted that none of the styles made to date would fit in the location due to its close proximity to the board frame. A new unit needed to be designed and 3D printed.
![]() |
| Geoff about to modify a standard unit. |

Farnham Show - 11-12 October 2025
On the Friday morning, Geoff and Stephen loaded their cars and drove to Farnham. Photo records of previous shows helped, but some modifications were required, and new record photos taken! Note two of the boards stacked vertically in their travelling frame.
The first stop was our hotel to book-in and meet with Ted, our guest operator, and have a cuppa! The school venue was undergoing serious work on a new building and access/parking had been fluid in the run-up to the event, but on the day, it worked out very well. Good access to our space meant unloading was 'short and simple' so the layout set-up went smoothly. We were amazed how much space was in front of us, an excellent working and viewing environment.
![]() |
A new timber wall, part of the full-length 3" front extension, which did get used and was very handy on occasions. It also allowed stock to be displayed closer to the viewers. |






















































